Audit History
Completed audits across the selected tenant.
72 completed audits
| Date | Zone | Site / Dept | Auditor | Shift | Score | |
|---|---|---|---|---|---|---|
| 12/30/1969 | QC Lab MX | Monterrey Plant · Quality | Jonas Lindqvist | Night | 82% | View |
| 12/29/1969 | Mantenimiento | Monterrey Plant · Maintenance | Mei Watanabe | Day | 60% | View |
| 12/29/1969 | Warehouse Rack A | Columbus Plant · Warehouse | Tomás Ríos | Day | 89% | View |
| 12/29/1969 | Línea de Ensamble | Monterrey Plant · Production | Jonas Lindqvist | Evening | 80% | View |
| 12/27/1969 | Empaque Línea 1 | Monterrey Plant · Packaging | Robert Kim | Evening | 64% | View |
| 12/26/1969 | Recibo | Monterrey Plant · Receiving | Hannah Becker | Evening | 70% | View |
| 12/22/1969 | Mantenimiento | Monterrey Plant · Maintenance | Mei Watanabe | Day | 66% | View |
| 12/22/1969 | Warehouse Rack B | Greenville Plant · Warehouse | Jonas Lindqvist | Day | 76% | View |
| 12/22/1969 | Warehouse Rack A | Columbus Plant · Warehouse | Aisha Mohammed | Day | 82% | View |
| 12/22/1969 | Recibo | Monterrey Plant · Receiving | Robert Kim | Day | 71% | View |
| 12/21/1969 | Assembly Line A | Columbus Plant · Production | Jonas Lindqvist | Night | 68% | View |
| 12/19/1969 | Assembly Line B | Columbus Plant · Production | Robert Kim | Day | 77% | View |
| 12/16/1969 | Warehouse Rack B | Greenville Plant · Warehouse | Robert Kim | Day | 78% | View |
| 12/15/1969 | Pick Aisle 1 | Reno Distribution · Warehouse | Jonas Lindqvist | Night | 74% | View |
| 12/14/1969 | Workstation A-12 | Columbus Plant · Production | Aisha Mohammed | Night | 57% | View |
| 12/13/1969 | Assembly Line A | Columbus Plant · Production | Robert Kim | Evening | 73% | View |
| 12/13/1969 | QC Lab MX | Monterrey Plant · Quality | Mei Watanabe | Day | 90% | View |
| 12/11/1969 | Maintenance Bay 2 | Greenville Plant · Maintenance | Aisha Mohammed | Day | 71% | View |
| 12/9/1969 | Outbound Staging | Reno Distribution · Shipping | Robert Kim | Night | 65% | View |
| 12/7/1969 | Receiving Dock | Columbus Plant · Receiving | Mei Watanabe | Evening | 79% | View |
| 12/7/1969 | Pick Aisle 1 | Reno Distribution · Warehouse | Robert Kim | Day | 72% | View |
| 12/6/1969 | Warehouse Rack B | Greenville Plant · Warehouse | Mei Watanabe | Evening | 75% | View |
| 12/4/1969 | Línea de Ensamble | Monterrey Plant · Production | Jonas Lindqvist | Day | 77% | View |
| 12/4/1969 | QC Lab MX | Monterrey Plant · Quality | Hannah Becker | Day | 89% | View |
| 12/1/1969 | Assembly Line A | Columbus Plant · Production | Aisha Mohammed | Day | 77% | View |
| 12/1/1969 | Mantenimiento | Monterrey Plant · Maintenance | Tomás Ríos | Evening | 68% | View |
| 12/1/1969 | Receiving Dock | Columbus Plant · Receiving | Aisha Mohammed | Night | 80% | View |
| 12/1/1969 | Workstation A-12 | Columbus Plant · Production | Mei Watanabe | Day | 58% | View |
| 11/30/1969 | Línea de Ensamble | Monterrey Plant · Production | Hannah Becker | Night | 73% | View |
| 11/28/1969 | Assembly Line B | Columbus Plant · Production | Aisha Mohammed | Day | 87% | View |
| 11/25/1969 | Pick Aisle 2 | Reno Distribution · Warehouse | Hannah Becker | Evening | 79% | View |
| 11/24/1969 | Maintenance Bay 2 | Greenville Plant · Maintenance | Hannah Becker | Evening | 73% | View |
| 11/24/1969 | Línea de Ensamble | Monterrey Plant · Production | Mei Watanabe | Day | 74% | View |
| 11/24/1969 | Pick Aisle 1 | Reno Distribution · Warehouse | Aisha Mohammed | Night | 70% | View |
| 11/22/1969 | Pick Aisle 2 | Reno Distribution · Warehouse | Robert Kim | Evening | 67% | View |
| 11/20/1969 | Workstation A-12 | Columbus Plant · Production | Jonas Lindqvist | Day | 53% | View |
| 11/18/1969 | Almacén Norte | Monterrey Plant · Warehouse | Mei Watanabe | Night | 82% | View |
| 11/18/1969 | Receiving Bay R | Reno Distribution · Receiving | Jonas Lindqvist | Night | 82% | View |
| 11/18/1969 | Packaging Line 2 | Columbus Plant · Packaging | Hannah Becker | Evening | 58% | View |
| 11/14/1969 | Recibo | Monterrey Plant · Receiving | Aisha Mohammed | Evening | 70% | View |
| 11/13/1969 | Packaging Line 1 | Columbus Plant · Packaging | Mei Watanabe | Day | 50% | View |
| 11/13/1969 | Mantenimiento | Monterrey Plant · Maintenance | Mei Watanabe | Night | 67% | View |
| 11/11/1969 | Receiving Bay R | Reno Distribution · Receiving | Aisha Mohammed | Day | 81% | View |
| 11/11/1969 | Línea de Ensamble | Monterrey Plant · Production | Tomás Ríos | Day | 82% | View |
| 11/9/1969 | Packaging Line 2 | Columbus Plant · Packaging | Tomás Ríos | Night | 47% | View |
| 11/7/1969 | Receiving Dock | Columbus Plant · Receiving | Hannah Becker | Evening | 81% | View |
| 11/7/1969 | Assembly Line A | Columbus Plant · Production | Aisha Mohammed | Evening | 74% | View |
| 11/6/1969 | Packaging Line 1 | Columbus Plant · Packaging | Aisha Mohammed | Day | 50% | View |
| 11/4/1969 | Almacén Norte | Monterrey Plant · Warehouse | Jonas Lindqvist | Day | 81% | View |
| 11/4/1969 | Pick Aisle 1 | Reno Distribution · Warehouse | Robert Kim | Day | 69% | View |
| 11/2/1969 | Assembly Line C | Greenville Plant · Production | Tomás Ríos | Night | 79% | View |
| 10/31/1969 | Warehouse Rack A | Columbus Plant · Warehouse | Jonas Lindqvist | Day | 90% | View |
| 10/31/1969 | Assembly Line C | Greenville Plant · Production | Jonas Lindqvist | Day | 74% | View |
| 10/30/1969 | Warehouse Rack A | Columbus Plant · Warehouse | Mei Watanabe | Evening | 79% | View |
| 10/28/1969 | Packaging Line 2 | Columbus Plant · Packaging | Mei Watanabe | Day | 57% | View |
| 10/27/1969 | Recibo | Monterrey Plant · Receiving | Jonas Lindqvist | Night | 74% | View |
| 10/25/1969 | Workstation A-12 | Columbus Plant · Production | Robert Kim | Evening | 56% | View |
| 10/24/1969 | Shipping Dock | Columbus Plant · Shipping | Mei Watanabe | Evening | 68% | View |
| 10/24/1969 | Recibo | Monterrey Plant · Receiving | Aisha Mohammed | Day | 80% | View |
| 10/24/1969 | Maintenance Bay 2 | Greenville Plant · Maintenance | Mei Watanabe | Evening | 64% | View |
| 10/21/1969 | Recibo | Monterrey Plant · Receiving | Tomás Ríos | Evening | 69% | View |
| 10/20/1969 | Shipping Dock | Columbus Plant · Shipping | Aisha Mohammed | Evening | 73% | View |
| 10/17/1969 | Pick Aisle 1 | Reno Distribution · Warehouse | Tomás Ríos | Day | 72% | View |
| 10/17/1969 | Shipping Dock G | Greenville Plant · Shipping | Jonas Lindqvist | Night | 72% | View |
| 10/17/1969 | QC Lab MX | Monterrey Plant · Quality | Mei Watanabe | Day | 89% | View |
| 10/16/1969 | Maintenance Bay 2 | Greenville Plant · Maintenance | Jonas Lindqvist | Day | 67% | View |
| 10/12/1969 | QC Lab MX | Monterrey Plant · Quality | Robert Kim | Night | 89% | View |
| 10/11/1969 | Packaging Line 1 | Columbus Plant · Packaging | Mei Watanabe | Night | 45% | View |
| 10/11/1969 | Línea de Ensamble | Monterrey Plant · Production | Mei Watanabe | Evening | 80% | View |
| 10/11/1969 | Línea de Ensamble | Monterrey Plant · Production | Aisha Mohammed | Evening | 75% | View |
| 10/9/1969 | Pick Aisle 2 | Reno Distribution · Warehouse | Tomás Ríos | Evening | 75% | View |
| 10/9/1969 | Pick Aisle 2 | Reno Distribution · Warehouse | Jonas Lindqvist | Evening | 79% | View |